In my process, i have 2 activites, the first is A, and the second is B.
I have 2 roles, one is C and another is D. D has only one person.
All user in role C must implement A, then only user in D can implement B.
The user in D implements B when all user in C is done his work.
How can i di this? any body gives me an idiea? thanks a lot! |
|
Back to top |
|
 |
jmac |
Posted: Mon May 15, 2006 6:30 am Post subject: Re: One question about mq workflow! |
|
|
 Jedi Knight
Joined: 27 Jun 2001 Posts: 3081 Location: EmeriCon, LLC
|
tyctlnc wrote: |
All user in role C must implement A, then only user in D can implement B. |
Role C contains U1, U2, U3. Are you saying that all of these users must work Activity A? If so, while this can be done it is non-trivial, and I would suggest that you get help from someone well versed in MQWF. _________________ John McDonald
RETIRED |
|
Back to top |
|
 |
anveshita |
Posted: Tue May 16, 2006 7:26 am Post subject: |
|
|
Master
Joined: 27 Sep 2004 Posts: 254 Location: Jambudweepam
|
I think I would need more information.
let us say u1, u2, u3 are under role C.
let us say u4 is under role D.
Do you want to carry the information processed by u1,u2,u3 to u4?
Do you want u1, u2, u3 to process the activity in parallel or
does the processing by u1 affect the processing of u2?
I agree with John, it is not trivial. One needs to have a clear picture of the
business before start modelling. |
|
Back to top |
|
 |
tyctlnc |
Posted: Sat May 20, 2006 8:42 am Post subject: |
|
|
Novice
Joined: 27 Apr 2006 Posts: 15
|
In my process, i want u4 to collect information from u1,u2,u3, then excution the active. |
|
Back to top |
|
 |
sarasu |
Posted: Wed May 24, 2006 6:13 am Post subject: |
|
|
Master
Joined: 02 Feb 2006 Posts: 229
|
In workflow, if the process is continuing from u1 to u2 and to u3, after that the result will go to u4? or you cannot make all the 3 activities with u1, u2 and u3 in parallel and then to u4. It depends on the conditions you check before starting the activity u4. Please let us know more clearly. |
|
Back to top |
|
 |
sarasu |
Posted: Wed May 24, 2006 6:16 am Post subject: |
|
|
Master
Joined: 02 Feb 2006 Posts: 229
|
You can also do in the Statrt Tab of the Activity properties of u4 user "All incomming "All incomming connectors are true" and then try it out. |
|
Back to top |
|
 |
|
|
 |
|